Heavy Equipment Movers

Heavy equipment moving glossary

Plain-English explanations of the terms you will come across.

Abnormal indivisible load
A load that cannot be split without undue cost or damage and that exceeds standard UK vehicle weight or size limits, so needs notification or authorisation to travel.
Appointed person
Under BS 7121, the competent person appointed to plan a crane lifting operation and to have overall control of it, from the lift plan through to the day.
Centre of gravity
The point where a machine's weight is balanced. Machines are often top-heavy or uneven, so knowing it is essential to lift and move them without tipping.
HIAB
A widely used name for a lorry loader, a crane mounted on a lorry that can load and unload its own cargo. The name comes from a well-known manufacturer.
Hydraulic gantry
A lifting system of hydraulic legs and a beam that raises heavy loads vertically, often used indoors where a crane cannot be used.
Lift plan
A written plan for a lifting operation setting out the load, lifting equipment, rigging, positions, exclusion zones, sequence and responsibilities, prepared before the lift.
Low-loader
A trailer with a low deck height used to carry tall or heavy machines while keeping the overall travelling height down for bridges and structures.
Machine skates
Low, heavy-duty roller units placed under a jacked-up machine so it can be rolled across a floor. Usually used in sets, with steerable skates at one end.
Method statement
A document describing step by step how a job will be carried out safely, usually issued with a risk assessment and often called RAMS.
Outriggers
Extending legs on a crane or HIAB that spread its load onto the ground for stability. Ground under them must be strong enough to carry the force.
Rigging
The planning and use of lifting and moving equipment, such as slings, shackles, jacks, skates and chain blocks, to move heavy loads safely and with control.
Safe working load
The maximum load a piece of lifting equipment is rated to lift in given conditions, marked on the equipment. Also referred to as working load limit.
Spreader beam
A rigid beam hung from a crane hook that spaces the slings apart, so the load is lifted evenly and the slings do not crush its sides.
Thorough examination
A detailed inspection of lifting equipment by a competent person required by LOLER, typically every six or twelve months depending on the equipment.
Toe jack
A compact hydraulic jack with a low lifting toe that fits under the base of a machine, used to raise it enough to fit skates or packers.